Probability distribution fitting of schedule overruns in construction projects

Author: Love P E D  

Publisher: Palgrave Macmillan Ltd

ISSN: 1476-9360

Source: Journal of the Operational Research Society, Vol.64, Iss.8, 2013-08, pp. : 1231-1247

Disclaimer: Any content in publications that violate the sovereignty, the constitution or regulations of the PRC is not accepted or approved by CNPIEC.

Previous Menu Next

Abstract

The probability of schedule overruns for construction and engineering projects can be ascertained using a `best fit' probability distribution from an empirical distribution. The statistical characteristics of schedule overruns occurring in 276 Australian construction and engineering projects were analysed. Skewness and kurtosis values revealed that schedule overruns are non-Gaussian. Theoretical probability distributions were then fitted to the schedule overrun data; including the Kolmogorov-Smirnov, Anderson-Darling and Chi-Squared non-parametric tests to determine the `Goodness of Fit'. A Four Parameter Burr probability function best described the behaviour of schedule overruns, provided the best overall distribution fit and was used to calculate the probability of a schedule overrun being experienced. The statistical characteristics of contract size and schedule overruns were also analysed, and the Wakeby (AU101 m) models provided the best distribution fits and were used to calculate schedule overrun probabilities by contract size.